Most remodels in Santa Clara County need a building permit once the work touches plumbing, electrical, mechanical systems, or structure. Cosmetic work like painting, new flooring, new countertops, and cabinet resurfacing usually does not. Additions, second stories, and ADUs need a building permit and often a planning approval before that. Every city runs its own building department, so the rules and timelines in San Jose differ from those in Saratoga, Cupertino, and their neighbors. This guide covers what triggers a permit, how long approval takes, and what each city adds on top of the state building code.

Which Remodeling Projects Need a Permit?

The line between “no permit” and “full plan review” follows the same logic in most cities. San Jose’s definitions are a useful reference because the city spells them out clearly: a minor remodel replaces fixtures and appliances with new electrical, plumbing, or mechanical work without moving them or adding more, while a major remodel changes walls or windows, modifies framing, or relocates or adds fixtures.

ProjectPermit needed?What to expect
Paint, new flooring, new countertops, cabinet resurfacingUsually noCosmetic work without electrical, plumbing, or structural changes.
Replacing fixtures and appliances in the same locationsYesOften a simple permit. San Jose issues minor kitchen and bath permits online at SJPermits.org.
Moving walls, windows, plumbing, or adding fixturesYesPlans and plan review, with inspections at key stages.
Whole-house remodelYesA comprehensive permit with structural and full mechanical, electrical, and plumbing plans, plus Title 24 energy compliance.
Addition or second storyYesA building permit, and often a planning approval or design review first.
ADUYesState law requires cities to decide on a complete ADU application within 60 days.
Electrical panel upgrade, heat pump, furnace or water heater replacementYesUsually a trade permit; many cities offer these online.

Santa Clara Permitting Guide - Bedroom

Planning Approval and Building Permits Are Two Separate Steps

Planning approval looks at what the project looks like and where it sits: height, setbacks, floor area, neighborhood fit, trees, and hillside impacts. It applies mainly to additions, second stories, and exterior changes. Building permits look at how the project is built: structure, fire safety, plumbing, electrical, mechanical systems, and energy code. Nearly every remodel that goes beyond cosmetic work needs a building permit. When a project needs both, planning approval usually comes first, and the building permit application follows once the design is approved.

How Long Do Remodeling Permits Take?

Timelines depend on the city, the scope, and how complete the first submittal is. Based on our projects and published city timelines:

  • San Jose: plan check for a comprehensive whole-house permit can take two months or more on its own. Smaller scopes move faster, and minor kitchen and bath remodels that keep fixtures in place can often be permitted online.
  • Smaller cities: in our experience, Los Gatos, Saratoga, Campbell, Sunnyvale, and Cupertino tend to move faster, while San Jose, Mountain View, and Los Altos tend to take longer.
  • Sunnyvale: the city publishes a 21-day first plan review for second-story additions (14 days for resubmittals), and interior remodels, or single-story projects of 800 square feet or less can get over-the-counter review. With corrections and resubmittals, standard addition permits typically take two months or more overall.
  • Design review: projects that need planning approval add that step before the building permit. In Saratoga, for example, administrative design review includes a 15-day neighbor comment period.
  • ADUs: under California law, a city must tell you within 15 business days whether an ADU application is complete, then approve or deny a complete application within 60 days. If it misses the 60-day deadline, the application is deemed approved.

The most common delay we see is a change in scope after plans are submitted, which sends the project back through plan check. Settling design decisions before submittal is the most reliable way to keep the permit phase on schedule.

Permit Rules by City

San Jose
Permits go through the city’s Development Services Permit Center, with online permits, fee payment, inspection scheduling, and permit records at SJPermits.org. Minor kitchen and bathroom remodels can qualify for an online permit; major remodels and additions go through plan review. The city recommends that a licensed contractor apply, and notes that whoever signs the application is responsible for all work under the permit. See our pages on ADUs in San Jose and whole home remodeling in San Jose.

Saratoga
Since April 2025, Saratoga reviews single-family projects against objective design standards. Adding a second story, expanding the existing second floor by 100 square feet or more, or increasing floor area by more than 50 percent triggers review. Projects that meet every standard are approved ministerially; projects that need an alternative design go to the Community Development Director or Planning Commission. Applications must map protected trees, hillside lots need site sections and engineered grading and drainage plans, and the Saratoga Woods neighborhood is limited to single-story additions. More on kitchen remodeling in Saratoga.

Cupertino
In single-family (R1) zones, a second-story addition needs a Two Story Permit before building permits. Added design review applies when the second floor exceeds 66 percent of the first floor or second-story side setbacks fall under 15 feet. Single-story overlay neighborhoods limit homes to one story and 18 feet, and a second story requires a Conditional Use Permit as well. The Fairgrove neighborhood is an Eichler district with its own design requirements. More on kitchen remodeling in Cupertino.

Los Gatos
Where full Architecture and Site approval isn’t required, the Town reviews a new second story or a second-story addition over 100 square feet through a minor residential review. Homes built before 1941, homes in a historic district, and designated landmarks go to the Town’s Historic Preservation Committee, and hillside projects often need geotechnical review. More on whole house remodeling in Los Gatos.

Los Altos and Los Altos Hills
In Los Altos, two-story additions and new two-story homes go through design review before the Design Review Commission. Los Altos Hills is a separate town with its own building department and review process. Additions over 500 square feet trigger school district impact fees and additional fire department review. More on home remodeling in Los Altos.

Mountain View
Mountain View does not have discretionary design review for single-family homes, which removes a step other cities require. Projects still need building permits, and adding 500 or more square feet of living space may be subject to school impact fees. More on kitchen remodeling and bathroom remodeling in Mountain View.

Sunnyvale
Single-story additions below the city’s floor area thresholds can be approved at staff level. Two-story projects and projects that exceed the thresholds (45 percent floor area ratio or 3,600 square feet in the R-1 zone, whichever is less) require public notice or a Planning Commission hearing. More on home additions in Sunnyvale.

What Changed for Permits in 2026

  • California’s 2025 Energy Code applies to building permit applications submitted on or after January 1, 2026. For additions, new or replacement space heating serving the addition must be a heat pump. Projects submitted before that date stay under the 2022 code.
  • ADU application timelines got stricter on January 1, 2026: a completeness decision within 15 business days, a written appeal process, and a final decision on appeals within 60 business days.

Santa Clara Permitting Guide - Bathroom

Who Should Pull the Permit?

Have your licensed contractor apply. The person who signs the application takes responsibility for the work under the permit, and San Jose warns homeowners about the liability of signing as an owner-builder when a contractor does the work. Before you hire anyone, check their license with the Contractors State License Board. Next Stage Design + Build holds California license #850885 and pulls permits for every project we build.

What Happens If You Remodel Without a Permit?

Skipping the permit rarely saves money in the long run. Without inspections, nobody independently checks that the structure, wiring, and plumbing meet code. Unpermitted work can come up when you sell: rooms may not count toward square footage, buyers can ask for credits or walk away, and lenders may hesitate. It also surfaces during future remodels, when a contractor needs accurate plans and finds work that was never inspected. Correcting it later can mean opening finished walls so an inspector can see the work.

How Next Stage Handles Permits

Permitting runs alongside design on every project we take on. Our design team measures your home and documents existing conditions, coordinates any engineering, and prepares the drawings each city requires. We submit planning and building applications, answer plan check comments, and schedule every inspection, while you work with your designer on material selections. Read more about our design-build process.

“We need to verify existing condition”

~Bess Cipriano, Architectural Designer, on what she tells clients before any permit drawings are drawn

Santa Clara Permitting Guide - Bath

Frequently Asked Questions About Remodeling Permits

Do I need a permit to remodel my kitchen in Santa Clara County?
If the remodel includes new electrical, plumbing, gas, or mechanical work, yes. Replacing fixtures and appliances in the same locations is usually a simple permit, while moving walls, windows, or plumbing requires plans and plan review. Cosmetic work like paint, new countertops, flooring, and cabinet resurfacing usually does not need a permit.

How long does a remodeling permit take in San Jose?
Plan check for a comprehensive whole-house permit in San Jose can take two months or more, with smaller scopes moving faster. Minor kitchen and bathroom remodels that keep fixtures in place can often be permitted online at SJPermits.org.

Which cities in Santa Clara County permit remodels fastest?
In our experience, smaller jurisdictions such as Los Gatos, Saratoga, Campbell, Sunnyvale, and Cupertino tend to move faster, while San Jose, Mountain View, and Los Altos tend to take longer. Scope, the completeness of the submittal, and any required design review matter as much as the city.

Do I need design review to add a second story?
In most Santa Clara County cities, yes. Saratoga, Cupertino, Los Gatos, Los Altos, and Sunnyvale all review second-story additions before a building permit is issued. Mountain View is an exception, with no discretionary design review for single-family homes.

How long does a city have to approve an ADU permit?
Under California law, a city must decide within 15 business days whether an ADU application is complete, and must approve or deny a complete application within 60 days. If it misses that deadline, the application is deemed approved.

Can I pull the permit myself as the homeowner?
You can in many cases, but whoever signs the application is responsible for the work. If a contractor is doing the work, have the licensed contractor apply, and verify their license with the Contractors State License Board first.

Does Next Stage handle permits for me?
Yes. We prepare drawings, submit planning and building applications, respond to plan check comments, and schedule all inspections in every city we work in.

Planning a Remodel in Santa Clara County?

Tell us about your home and what you want to change. We’ll outline the approvals your project needs in your city and how they fit into the schedule.